enet engineer working on a distillation plant

Modernization of a Distillation Plant

Pharma
August 2023
The existing S7 controller with Wonderware visualization was replaced by a PCS 7 system, which minimized downtime thanks to parallel operation. The distillation plant was then expanded from one to three columns, including a new control cabinet system. The control and function logic was newly developed and optimized together with Vogelbusch and Schmidberger.

Toolbox

PCS 7
Safety

Stage 1

Upgrade to PCS 7:

The existing S7 control program and the existing Wonderware visualization were replaced by a new PCS 7 program with the same functionality.

During the commissioning phase, the new PCS 7 controller (CPU AS 410) was set up in parallel with the existing S7-400 controller. The existing ET 200iSP I/O hardware remained unchanged, so it was possible to switch back to the old S7-400 controller with the old Wonderware visualization at any time and keep downtime to a minimum.

 

Stage 2

Mechanical extension of the distillation plant and extension of its functionality:

In collaboration with our main contractor Vogelbusch Biocommodities, the distillation plant was completely redesigned and expanded (3 columns instead of 1) to enable, among other things, increased flow rates and less downtime.

In this context, a control cabinet system was built in cooperation with Schmidberger and linked to the existing switchgear. As a result of the expansion of the mechanical components, the functionality and thus the program logic were also redesigned or expanded in collaboration with process engineers from Vogelbusch.

‍

Benefit

‍Strong focus on easy operability, increased throughput, reduced downtime during operation and conversion phase, and consequently a short shutdown.